# A complex of works on the connection of the AKSA APD 1650 M diesel generator set for “Vetropak Gostomelskyi Sklozavod”

For "Vetropak Gostomelskyi Sklozavod" company, our company performed a complex of works on connecting the AKSA APD 1650 M diesel generator set in the amount of 2 pcs. The list of complex construction and assembly works included: - Installation of the foundation for the installation of diesel generators and generators; - Installation of the grounding device; - Installation of lightning protection with a separate grounding circuit; - Installation of overpass and cable laying systems; - Installation and connection of power cables; - Installation of the necessary number of РУ-0.4kV cells with the necessary equipment; - Complex of measurement of leakage resistances on grounding devices; - Complex of КЛ tests; - ПНС of generators and operating modes of capacity limitation; - Development of project and executive documentation.

LEARN MORE
# Electrical installation works with the supply of equipment for the modernization of ПС35/10 kV, “Zukrozavod – Zbarazh”

LEARN MORE
# Reconstruction РП – 27

Our company performed the reconstruction of RP-27 for the customer PJSC "Zaporizhjiaoblenergo". Cells with vacuum switches of own production "Energy Group" were delivered to the facility. A complex of works was also carried out, which included: - project development; - installation; - adjustment works Shipment to the facility and all works included in the complex were done quickly, and most importantly, with high quality!

LEARN MORE
# Block complete transformer substation for “Chernigovoblenergo”

Our company "Energy Group" has produced a block complete transformer substation, which is a flexible solution for powering objects of any kind. The block complete transformer substation is assembled from a monolithic block, which allows you to protect the installed equipment from the effects of weather conditions and maintain the stable operation of the equipment for a long time. It has metal doors on both sides, which are equipped with internal locks. From the outside, the structure is covered with water-repellent plaster, namely marble crumb, which prevents moisture from getting inside. The roof is made in accordance with existing norms and requirements and protects against the penetration of precipitation inside the structure.

LEARN MORE
# Delivered a complete transformer substation

Our company Energy Group delivered a complete transformer substation for the customers of Poltavahazvydobuvannya and Shebelynkahazvydobuvannya.

LEARN MORE
# KTP 2x1000kva, installation work and cable laying on the overpass at the facility

Work on the facility in the village village Khrestyshche. A complete 2x1000 kVA transformer substation, control cabinets with frequency converters and a complete 3150 kVA transformer substation for connecting diesel generators were delivered to the work site. Installation work was also carried out and the laying of the cable along the overpass was carried out.

LEARN MORE
# Emergency and restoration repair of PL-10 kV Tsirkuny

After the end of the military operations in the Kharkiv region, Energy Group carried out emergency and recovery repairs of PL-10 kV Tsyrkuny. During the works, 8 km of 10 kV electric-overhead line were restored, damaged supports (more than 80 pieces), traverses and insulators were replaced, new disconnectors and all other necessary electrical equipment were installed. Sicame high-voltage fittings were used during installation.

LEARN MORE
# Power substation “Zhukovsky”

We have completed the construction of the construction and supply of a complete, enclosed, enclosed enclosure of the 10 kV type, which is assembled from KЗO-319, on the basis of Schneider Electric electrical control and a microprocessor attachment, automation, control, and installation of the MRZS series.

LEARN MORE
# КТП 1000 kVA for “Kharkiv Metro”

The work was completed in the shortest possible time, taking into account all the requirements and wishes. In the manufacture of КТП, Ukrainian-made materials were used to the maximum. Thanks to the КТП, which has a quick installation and ease of transportation, ease of connection and commissioning, it is possible to restore power to damaged objects for their further operation. Considerable attention should also be paid to the modern method of powder painting, which has a significant share of advantages, namely: resistance to abrasive abrasion, resistance to temperature changes, impact resistance, excellent protection against corrosion.

LEARN MORE
# Avangard, Residential Complex “Grekiv Lis”

Production of another product from our company Energy group - КРПЗ. This time, we supplied КРПЗ - 10 kV and КРПЗ - 35 kV. The complete closed-type switchgear was manufactured by order of Avangard for the residential complex "Grekiv Lis". The metal structure of the КРПЗ in our case is easy to mount and has a modern and practical design. КРПЗ-10 and 35 kV were delivered to the installation site in separate transportable units and assembled on the territory of the substation. The КРПЗ blocks were equipped with cells of modern complete switchgears at the production site. After the successful delivery of the equipment, a full range of works on installation, connection and testing is carried out.