Overhaul of the “Stepanovka” 35/10 kV transformer substation for “Sumyoblenergo” LLC
As part of the capital repair of the TP, the supply and replacement of three VM-35 type oil switches with BP-35 NSM vacuum switches, as well as the replacement of RZA chains, were made.
After the completion of the preparatory work, our company delivered and installed the RZA and vacuum switches. The work was carried out in the conditions of a functioning energy facility in one stage. The work on the laying of a high-voltage power cable with cross-linked polyethylene insulation and testing work was completed.