Power supply device for PJSC “Ukrnefteburenie” Mining Company”
During the quarantine, EnergyGroup performed work on the supply and installation of electrical equipment for Ukrnefteburenie. Completed reconstruction of the 6 kV overhead line with a length of 4.5 km, delivery of a complete KTП-1600 kVA transformer substation manufactured by EnergyGroup with a Tesar dry transformer. Despite the closed border and interruptions in transport logistics, EnergyGroup fulfilled all its obligations, the commissioning of the installed equipment took place on time.