triangles decor triangles decor
#
#
#
#
#
#

Power supply device for PJSC “Ukrnefteburenie” Mining Company”

Power supply device for PJSC “Ukrnefteburenie” Mining Company”

During the quarantine, EnergyGroup performed work on the supply and installation of electrical equipment for Ukrnefteburenie. Completed reconstruction of the 6 kV overhead line with a length of 4.5 km, delivery of a complete KTП-1600 kVA transformer substation manufactured by EnergyGroup with a Tesar dry transformer. Despite the closed border and interruptions in transport logistics, EnergyGroup fulfilled all its obligations, the commissioning of the installed equipment took place on time.

Presentation video Company «Energy Group»

Watch
promo video

    Request a call back